Monthly Archives: March 2012

16- Near Completion

Links Projects Update March 29, 2012 The pond restoration work on 16 is about 90% complete.  16,000 square feet of sod has been installed around the pond and across fairways #17 and #18 along with some seeding in a few … Continue reading

Posted in Home, Notices | 1 Comment

#16- Sodding Begins

We have started sodding around the 16th pond. The 12,000 square feet will be installed today with another 6000 sq ft delivered tomorrow. The road across fairways 17 and 18 will be prepped and the sod installed tomorrow. We will … Continue reading

Posted in Home, Notices | Leave a comment

#16- Sod Preparation

We have been preparing the area around the #16 pond for sod which will be delivered on Tuesday and Wednesday of next week.

Posted in Home, Notices | Leave a comment

#4 Clean-Up Excavation

The pond on #4 and the ditch on #3 were excavated on Monday and Tuesday. The construction zone for the pond at #16 is getting prepared with topsoil and we should be sodding this site early next week. Topsoil and … Continue reading

Posted in Home, Notices | Leave a comment

Work on #4 Begins

The work on #4 has begun with the goal being a similar look to #16.

Posted in Home, Notices | Leave a comment

Fixing Ball Marks

Posted in Golf Etiquette, Home | Leave a comment

#16 Day 5

The clean up of the temporary road began today. The areas to the right of #3 and #4 will be the next areas to be cleaned up. The next step on #16 will be to prep the area for sodding.

Posted in Home, Notices | Leave a comment